VSC HVDC Example- Murray link
• Commissioning
year:2002
• Power rating: 220 MW
AC
• Voltage:132/220 kV
• DC Voltage:+/- 150 kV
• DC Current: 739 A
• Length of DC cable:2 x
180 km
VSC HVDC Example- Troll
Commissioning year:
2005
• Power rating: 2 x 42
MW AC Voltage:132 kV
at Kollsnes, 56 kV at
Troll
• DC Voltage: +/- 60 kV
• DC Current: 350 A
• Length of DC cable:4 x
70 km
488 trang |
Chia sẻ: linhmy2pp | Ngày: 19/03/2022 | Lượt xem: 187 | Lượt tải: 0
Bạn đang xem trước 20 trang tài liệu Bài giảng Trang thiết bị điện trên hệ thống truyền tải điện - Nguyễn Hữu Phúc, để xem tài liệu hoàn chỉnh bạn click vào nút DOWNLOAD ở trên
uite
uncommon.
The valve windings are exposed to AC and DC dielectric stress
and therefore a special insulation assembly is necessary. Furthermore,
special lead systems connecting the turrets and windings have to be
installed in order to withstand the DC voltage of rectifier. Additionally, the
load current contains harmonic components of considerable energy
resulting in higher losses and increased noise. Above all, special
bushings are necessary for the valve side to access upper and lower
winding terminals of each system from outside. Conclusively, two
identical bushings are installed for star or delta system.
Phase Shifting
Transformers
Phase shifting transformers are used to control the
phase angle across the transformer
Since power flow through the transformer depends
upon phase angle, this allows the transformer to
regulate the power flow through the transformer
Phase shifters can be used to prevent inadvertent
"loop flow" and to prevent line overloads.
Phase Shifter
345.00 kV 341.87 kV
283.9 MW 283.9 MW
39.0 Mvar 6.2 Mvar
500 MW slack
164 Mvar 500 MW
100 Mvar
Phase Shifting Transformer
216.3 MW 216.3 MW
125.0 Mvar 0.0 deg 93.8 Mvar
1.05000 tap
ComED Phase Shifter Display
Phase shifting transformer
Voltage angle adjustment.
UU
P=12 sinδ+α
X
2
U1 UU
Q=12 cosδ+α
XX
Phase shifting transformer
• Allows for some control over active power flows
• Mechanically switched ==> minutes
UU
P= 12sinδ+α
X+XPST
Phase shifting transformer (II)
Principles
• Injection of a voltage in quadrature of the phase
voltage
• One active part or two active parts
Asymmetric Symmetric
D U
25 ° ==> 10 % voltage rise
==> 40 kV @ 400 kV
Power Flow in Parallel Circuits
Phase Shifting XFMR
Fig. A/
Fig.B/
• A Phase Shifting XFMR
schematic is shown in Fig. B/
operating in a three-phase
power system.
• In practice, the configuration
in Fig .C/ is preferred because
it can keep identical
modules while allowing
Fig. C/
phase adjustment between
input voltages and output
voltages. It is the type of
construction in use for
transformers in France.
>> In Fig. is shown a Phase
Shifting XFMR of 65 MVA installed
in Sainte-Cecile substation
(France). It is the first of its type
installed in 63 kV network and
allows forcing more power flow
on the line Sainte-Cecile-Vaison
and, at the same time, relieving
the other two lines Chateauneuf-
du-Rhone– Montmartel and
specially, the line Montmartel-
Valaurie, which are both near
their capacity limits. The numbers
shown in Fig. are the percent of
the line power flow capacity,
without parentheses before XFMR
installation and with parentheses
after.
>> In 2009, in France there were 6 more XFMRs existing in HV lines, 4 of of 225 kV in Pyrenees
region, 1 of 400 kV in Savoie and 1 of 90 kV in Pas de Calais.
The characteristics of these XFMRs are as follows:- site of La Paz: 400kV - Capacity: 1081 MVA-
phase shifting adjustment between 5.5 ° and – 14.5 ° by means of on-load tap changers of 33
positions.
Phase shifting transformer (III) One active part
• Series voltage injection
• In quadrature to the phase voltage
• One active part: low power/low voltage (high shortcircuit
currents at low angle)
3' 1' 2'
3 3'
Voltages over
coils on the same
transformer leg
are in phase
1 2
1 2 3
Phase shifting transformer- Regulating
• Changing injected voltage:
– Tap changing transformer
– Slow changing of tap position: ½
min
• Control of the injected voltage:
– Centrally controlled calculations
– Updates every 15 minutes
– Often remote controlled
– Can be integrated in WAMS/WACS
system
Phase shifter influence
Base case
1018 MW 500 MW
A B
G G
Slack bus 500 MW 1000 MW
344.3 MW
173.5 MW 170.4 MW
Flow of A to B gets
C distributed according to
G
800 MW the impedances
losses: 18 MW 800 MW
Phase shifter influence
1 phase shifter placed
1024.6 MW 500 MW
A B
G G
500 MW 1000 MW
491.8 MW
15 °
32.8 MW
33 MW
C Flow of A to B is taken
G
800 MW mostly by line A-B
losses: 24.6 MW 800 MW
Phase shifter influence
1 phase shifter placed: overcompensation
1034 MW 500 MW
A B
G G
500 MW 1000 MW
580 MW
30 °
42.3 MW
41.4 MW
C Overcompensation
G causes a circulation
800 MW current
800 MW
losses: 34 MW
Phase shifter influence
2 phase shifters: cancelling
1052.3 MW 500 MW
A B
G G
500 MW15 ° 1000 MW
313.9 MW
15 °
221 MW
238.4 MW
C The phase shifting
G transformers can
800 MW cancel their effects
losses: 52.3 MW 800 MW
Phase shifter influence
2 phase shifters: cancelling
FLOWS relative to base case (no PS)
1052.3 MW 500 MW
A B
G G
500 MW15 ° -8.8 % 1000 MW
313.9 MW
15 °
221 MW
238.4 MW +14.6 %
+18.8 %
When badly
C controlled, little
G influence on flows,
Additional losses: 800 MW more on losses
+ 34.4 MW 800 MW
Phase shifter influence
2 phase shifters: fighting
FLOWS relative to base case (no PS)
10541052.3 MW MW 500 MW
A B
G G
500 MW 30 -°8.8 % 1000 MW
259.7 MW
15 313.9 MW
15 ° ° 221 MW
238.4 MW 259.7 MW
294.3 MW +14.6 %
+18.8 %
The Whenphase badly shifting
C controlled, little
G transformersinfluence on flows, can
800 MW more`fight' on losses
Additionallosses: 54 losses: 800 MW
+ 34.4MW MW
Phase shifter influence
2 phase shifters: fighting
FLOWS relative to base case (no PS)
1054 MW 500 MW
A B
G G
500 MW15 ° -24.5 % 1000 MW
259.7 MW
30 °
259.7 MW
294.3 MW +28 %
+35 %
C The phase shifting
G transformers can
800 MW `fight'
losses: 54 MW 800 MW
Phase shifters in Belgium
• Zandvliet – Zandvliet
• Meerhout – Maasbracht (NL)
• Gramme – Maasbracht (NL)
– 400 kV
– +/- 25 ° no load
– 1400 MVA
– 1.5 ° step (34 steps)
• Chooz (F) – Monceau B
– 220/150 kV
– +10/-10 * 1.5% V (21 steps)
– +10/-10 * 1,2° (21 steps)
– 400 MVA
Transformer Mechanical Construction
three-leg transformer
The magnetic return paths of the three cores can be dropped, which results in the usual type of three-phase transformers.
One primary and one secondary winding of a phase is arranged on any leg.
a/ shell-type transformer b/ core-type transformers
Five-leg transformers are used for high low overall height high magnetic leakage low magnetic leakage
power applications (low overall height).
windings: low-leakage models
•joints: air gaps are to be avoided
a/ cylindrical winding b/ double cylindrical winding c/ disc winding/sandwich winding
•core cross sections: adaption to circle
VA kVA MVA
Tank Heating of Three-Legged Core Transformers
Zero-sequence flux in three-legged core
transformers enters the tank and the
air and oil space.
■ Zero-sequence fluxes will ―escape‖ the core on three-legged core designs (the most
popular design for utility distribution substation transformers). The 3d, 9th, 15th, etc.,
harmonics are predominantly zero-sequence. Therefore, if the winding connections are proper
to allow zero-sequence current flow, these harmonic fluxes can cause additional heating in the
tanks, core clamps, etc., that would not necessarily be found under balanced three-phase or
single-phase tests.
Tertiary Winding of Transformer
1. What is tertiary winding? What is Three Winding Transformer ?
In some high rating transformer, one winding, in addition to its primary and secondary winding, is used. This additional winding, apart
from primary and secondary windings, is known as Tertiary Winding of Transformer. Because of this third winding, the transformer
is called Three Winding Transformer or 3 Winding Transformer.
2. Advantages of using tertiary winding in transformer
Tertiary Winding is provided in Electrical Power Transformer to meet one or more of the following requirements:
i. It reduces the unbalancing in the primary due to unbalancing in three phase load
ii. It redistributed the flow of fault current
iii. Sometime it is required to supply an auxiliary load in different voltage level in addition to its main secondary load. This secondary
load can be taken from tertiary winding of three winding transformer.
iv. As the tertiary winding is connected in delta formation in 3 winding transformer, it assists in limitation of fault current in the
event of a short circuit from line to neutral.
3. Stabilization by tertiary winding of transformer
In star - star transformer comprising three single units or a single unit with 5 limb core offers high impedance to the flow of
unbalanced load between the line and neutral. This is because, in both of these transformers, there is very low reluctance return path
of unbalanced flux.
If any transformer has N - turns in winding and reluctance of the magnetic path is RL, then,
mmf = N.I = ΦRL ....... (1)
Where I and Φ are current and flux in the transformer.
Again, induced voltage V = 4.44ΦfN
⇒ V ∝ Φ
⇒ Φ = K.V (Where K is constant)....... (2)
Now, from equation (1) & (2) , it can be rewritten as,
N.I = K.V.RL
⇒ V/I = N/(K.RL)
⇒ Z = N/(K.RL)
⇒ Z ∝ 1/RL
From this above mathemetical expression it is found that impedance is inversely proportional to reluctance. The impedance
offered by the return path of unbalanced load current, is very high where very low reluctance return path is provided for unbalanced
flux.
Three Winding Transformer
In other words, very high impedance to the flow of unbalanced current in 3 phase system between line and neutral.
Any unbalanced current in three phase system can be divided in to three sets of components like wise positive sequence,
negative sequence and zero sequence components.
The zero sequence current actually co-phasal current in three lines. If value of co-phasial current in each line is Io, then total
current flows through the neutral of secondary side of transformer is In = 3.Io.
This current can not be balanced by primary current as the zero sequence current can not flow through the isolated neutral
star connected primary. Hence the said current in the secondary side set up a magnetic flux in the core.
Low reluctance path is available for the zero sequence flux in a bank of single phase units and in the 5 limb core,
consequently the impedance offered to the zero sequence current is very high.
The delta connected tertiary winding of transformer permits the circulation of zero sequence current in it.
This circulating current in this delta winding balances the zero sequence component of unbalanced load, hence prevent
unnecessary development of unbalanced zero sequence flux in the transformer core.
In few words it can be said that, placement of tertiary winding in star - star - neutral transformer considerably reduces
the zero sequence impedance of transformer.
4. Rating of tertiary winding of transformer
Rating of tertiary winding of transformer depends upon its use. If it has to supply additional load, its winding cross -
section and design philosophy is decided as per load and three phase dead short circuit on its terminal with power flow from
both sides of HV & MV.
In case it is to be provided for stabilizing purpose only, its cross - section and design has to be decided from thermal and
mechanical consideration for the short duration fault currents during various fault conditions single line - to - ground fault
being the most onerous
Three Winding Transformers
5. What is need of tertiary winding in transformers?
Tertiary windings generally serve one of two purposes.
1. One purpose may simply be to provide an additional terminal, often at a different voltage. While the use
of ‗three winding transformers' is relatively unusual, it can be a powerful tool is system architecture.
2. The other objective for a tertiary winding is to provide a closed-circuit path for zero-sequence
currents/fluxes.
That is most typically the case with transformers that, for system reasons, must be connected wye-wye
(star-star for those in the IEC world).
With a wye-wye transformer, the only path for zero-sequence flux is the tank of a transformer (and if the
three-phase bank is comprised of three single-phase units, even that does not exist).
The tank is a high-impedance path, so the result is that the zero sequence impedance seen looking into
the transformer is very high.
Also, the circulation of zero sequence current through the tank will cause the tank to heat and lead to paint
failure.
A tertiary winding presents a low impedance path to zero sequence currents, thereby reducing the
zero sequence impedance presented to the outside world, while avoiding the problem of tank
heating.
Maintenance of Power Transformer
Instruction Manual
Weekly Check
Please conduct weekly check in operating condition once per 1 or 2 weeks.
It is to confirm the operating condition of the transformer visually, find the
abnormality in early stages and prevent accidents.
Please use binoculars when you check the top of the transformer visually.
When the control criteria are not met, please contact TMT&D.
Special inspection is necessary in some cases
Inspection point Inspection item Inspection procedure Control criterion and remedy
Oil leak Check if there is oil leak from No oil leak
the gasket or the weld.
General
Rust, damage Check if there is rust or damage. No marked rust or damage
Bolts and nuts Check if they are not missing. No missing
Transformer Operating sound, Check if there is abnormal noise No abnormal noise or foreign odor
body foreign odor or foreign order.
Gauges in Internal moisture Visually check if there is moisture No moisture condensation
general condensation condensation inside the glass of
gauges.
Oil temperature Temperature Check and record temperature The indication should be much
indicator indication indication as well as load factor the same as the past measured
and outside air temperature of data (in condition of approxi-
the transformer. mate load factor and outside
air temperature).
Winding Temperature Check and record temperature The indication should be much
temperature indication indication as well as load factor the same as the past measured
indicator and oil temperature (temperature data (in condition of approxi-
indication of the oil temperature indicator)of the mate load factor and oil tempe-
transformer. rature).
Resistance bulb Temperature Check temperature indication of The difference of temperature
For oil temperature indication the resistance bulb and the oil temperature indicator. indications between the
resistance bulb and the oil temperature
indicator should
be 5°C or less.
Winding Temperature [In case that winding temperature The difference of temperature
temperature indication indicator is attached] indications between the winding
transmitter Check temperature indication of temperature transmitter and the winding
the winding temperature transmitter and the winding temperature
temperature indicator. indicator should be 5°C or less.
[In case that winding temperature The indication should be much
indicator is not attached] the same as the past measured
Check and record temperature data (in condition of approxi-
indication as well as load factor mate load factor and oil
and oil temperature (temperature temperature).
indication of the oil temperature indicator)of the
transformer.
Oil level Oil level Check oil level indication as well The oil level indication should
gauge (except for indication as oil temperature (temperature be within the allowable range
one for bushing) indication of the oil temperature indicator). of the oil level monitoring
curve.
Inspection point Inspection item Inspection procedure Control criterion and remedy
Degree of Check the color of the desiccant If the desiccant turns from blue
dehydration through the inspection window. to pink, replace it.
(See “Instructions for
Dehydrating Breather” for
replacement procedure.)
Oil level Visually check the oil level in the If the oil level is below the oil
oil pan. level line (red line), refill with
oil to the level of the line.
(See “Instructions for
Dehydrating Breather” for
oil refill procedure.)
Dehydrating Drift of oil and Check the dirt condition of oil and If the oil pan or the desiccant is
breather desiccant desiccant in the oil pan. significantly dirty, renew the
oil, and clean the oil pan and
the desiccant.
(See “Instructions for
Dehydrating Breather” for
procedures of changing oil and
cleaning the oil pan and the
desiccant.)
Operation of Check if bubbles go in and out Bubbles should go in and out.
breathing through the tip of the breathing
pipe in the oil pan when the
temperature changes.
Pressure relief Oil spillage Visually check any trace of oil spillage at There should be no trace of oil
device [In case a oil the bottom of the oil discharge pipe. spillage.
discharge pipe If there is any oil spillage, a special
is attached] inspection of the interior of the
pressure-relief device is required.
Contact TMT&D.
Target condition Visually check the presence/absence of The target should not be erect.
[In case a target is attached] the If the target is erect, oil spillage may
target operation. be suspected. Check any trace of oil
spillage.
If there is any oil spillage, a special
inspection of the interior of the
pressure-relief device is required.
Contact TMT&D.
Drain valve Penetration of Open the drain valves of the There should be no rainwater
rainwater terminal box for low voltage discharge from the drain valve.
bushing and the bus duct to check It may be due to leaks on the
discharge of rainwater visually. IPB.
Close the drain valves after Please contact the IPB
inspection. manufacturer.
Inspection point Inspection item Inspection procedure Control criterion and remedy
Air bushing Dirt, breakage Visually check if there is dirt or If the porcelain tube is signifi-
damage on the porcelain insulator. cantly dirty, stop the circuit
securely for the occasion and
clean the porcelain tube.
(See “Instructions for Bushing” for cleaning procedure.)
If there is a breakage, please
contact TMT&D.
Oil leak Visually check if there is oil leak. There should be no oil leak.
If you leave oil leak, it may
lead to dielectric breakdown
due to oil level decrease.
Oil level gauge Oil level [In case of dial type indication] The oil level indication should
for bushing indication Check the oil indication. be between H and L or 5% and
100%.
If it is out of the control criteria,
it may be due to oil leak of the
bushing.
[In case of direct-view indication] The float should float on the
Visually check the state of the oil.
float through the inspection window. If it is out of the control criteria,
it may be due to oil leak of the
bushing.
Radiator Corrosion of Check if there is corrosion. No marked corrosion.
cooling pipe
Cooling fan Operating sound Check the operating sound of the No abnormal noise.
of the cooling fan cooling fan.
Operating Check the operating condition of The cooling fan that should be
condition of the cooling fan. running should not be stopped.
the cooling fan
Oil pump Operating sound Check the operating sound of the No abnormal noise.
of the oil pump oil pump.
Operating Check the indicated direction of The oil pump that should be
condition of the oil flow indicator. (During running should not be stopped.
the oil pump operation: FLOW, during halt:
STOP)
Forced-oil Operating sound Check the operating sound of the No abnormal noise.
forced-air of the cooling fan and the oil pump cooling fan and the oil pump.
cooling
Operating Check the operating condition of The cooling fan and the oil
equipment
condition of the the cooling fan. pump that should be running
cooling fan and Check the indicated direction of should not be stopped.
the oil pump the oil flow indicator. (When
the oil pump is operating: FLOW,
when stopped: STOP)
Inspection Control criterion and
Inspection item Inspection procedure
point remedy
Forced-oil Operating sound Check the operating sound of No abnormal noise.
forced-water of the oil pump the
cooling oil pump.
equipment Operating Check the indicated direction The oil pump that should be
condition of the of running should not be
oil pump the oil flow indicator. (During stopped.
operation: FLOW, during halt:
STOP)
Coolant level Check the coolant level with a The prescribed amount of
coolant gauge. water should flow.
Coolant leak, Check if there is coolant leak No coolant leak or oil leak.
oil leak or
oil leak through the inspection
window of the leak detector.
On-load tap See “Instructions for On-load Tap Changer” for inspection items, inspection procedures,
changer control criteria and remedies.
Motor-driven See “Inspections for Motor -Driven Operating Mechanism” for inspection items, inspection
operating procedures, control criteria and remedies.
mechanism
Hot line oil See “Inspections for Hot Line Oil Purifier” for inspection items, inspection procedures,
purifier control criteria and remedies.
Periodic Inspection
Please conduct periodic inspection after stopping operation at regular
periods.
Mainly for the points that cannot be checked during weekly check, external
inspection of abnormality, internal diagnosis with measuring devices and
performance test are conducted to maintain the performance.
When the control criteria are not met, please contact TMT&D. Special
inspection is necessary in some cases.
5. High Voltage Circuit Breakers
Phu My- Ho Chi Minh City
(Phu My - Nha Be - Phu Lam)
500 kV Transmission Line Project
Package#1 substation works
Circuit-Breaker technical description
3. Circuit Breakers
A high-voltage circuit breaker is an indispensable piece of equipment in the
power system.
The main task of a circuit breaker is to interrupt fault currents and to isolate
faulted parts of the system.
Besides short-circuit currents, a circuit breaker must also be able to interrupt a
wide variety of other currents at system voltage such as capacitive currents,
small inductive currents, and load currents.
We require the following from a circuit breaker:
• In closed position it is a good conductor;
• In open position it behaves as a good isolator between system parts;
• It changes in a very short period of time from close to open;
• It does not cause overvoltages during switching;
• It is reliable in its operation.
•The electric arc is, except from power semiconductors, the only known element
that is able to change from a conducting to a nonconducting state in a short period
of time.
•In high-voltage circuit breakers, the electric arc is a high-pressure arc burning in oil,
air, or sulphur hexafluoride (SF6).
•In medium-voltage breakers more often, the low-pressure arc burning in vacuum is
applied to interrupt the current. The current interruption is performed by cooling the
arc plasma so that the electric arc, which is formed between the breaker contacts
after contact separation, disappears.
•This cooling process or arc-extinguishing can be done in different ways. Power
circuit breakers are categorised according to the extinguishing medium in the
interrupting chamber in which the arc is formed.
•That is the reason why we speak of oil, air-blast, SF6, and vacuum circuit breakers
It becomes clear that current interruption by an electrical arc is a complex physical
process when we realise that the interruption process takes place in microseconds,
the plasma temperature in the high-current region is more the 10 000 K, and the
temperature decay around current zero is about 2000 K/μs per microsecond while
the gas movements are supersonic.
.
3.1 THE SWITCHING ARC
Figure 3.1 The arc channel can be divided into an arc column, a cathode, and an anode
region
Figure 3.2 Typical potential distribution along an arc channel
3.2 SF6 CIRCUIT BREAKERS
Figure 3.3 Operating principle of an SF6 puffer circuit breaker
3.3 VACUUM CIRCUIT BREAKERS
Figure 3.4 Vacuum interrupter with slits in the contacts to bring the arc in a spiralling motion
3.4 ARC–CIRCUIT INTERACTION
•Current interruption of a circuit breaker occurs normally at current zero within a
time frame of microseconds. In the process of current interruption, several
processes take place at the same time.
•The arc voltage after maintaining a constant value during the high current interval,
increases to a peak value, the extinction peak, and then drops to zero with a very
steep du/dt.
•The current approaches its zero crossing with a more or less constant di/dt but
can be slightly distorted under the influence of the arc voltage.
•The arc is resistive and therefore the arc voltage and the current reach the zero
crossing at the same instant.
•Around current zero, the energy input in the arc channel is rather low (at current
zero there is even no energy input), and when the breaker design is such that the
cooling by the extinguishing medium is at its maximum, the current can be
interrupted.
•After current interruption, the still-hot gas between the breaker contacts is
stressed by a steep rate of rise of the recovery voltage and in the resulting
electric field the present charged particles start to drift and cause a hardly
measurable so-called post-arc current.
•The post-arc current, together with the transient recovery voltage, results in
energy input in the still-hot gas channel.
•When the energy input is such that the individual gas molecules dissociate into
free electrons and heavier positive ions, the plasma state is created again and
current interruption has failed.
•This is called a thermal breakdown of the circuit breaker.
•When the current interruption is successful, the hot gas channel cools down
and the post-arc current disappears; still a dielectric failure can occur when the
dielectric strength of the gap between the breaker contacts is not sufficient to
withstand the transient recovery voltage.
Figure 3.5 Simple lumped-element
representation of the network connected to
the breaker terminals
The simplest lumped element representation of the power system, as seen from
the terminals from the circuit breaker, consists of a voltage source with the value
of the system voltage, an inductance with the value of the total short-circuit
inductance, a capacitance resembling the stray capacitance of the bus bars,
voltage transformers, current transformers, and power transformers in the
substation.
In parallel with this capacitance, a resistor simulates the characteristic impedance
of the connected overhead lines
Zs = √(Ls/C) is the characteristic impedance
•For testing purposes, the short-circuit currents are divided in so-called duties, each
covering a percentage of the full short-circuit current.
•The IEC 60056 high-voltage circuit breaker standard distinguishes for the breaker
terminal fault duties the 10%, 30%, 60% and 100% current ratings.
•To each duty a specific rate of rise of the recovery voltage is specified and this enables
us to calculate the characteristic impedance of the connected network.
•For instance, for a 100 percent short-circuit current of a 145 kV–40 kA–50 Hz circuit
breaker, the specified du/dt is 2000 V/μs and the di/dt is 0.444 ∗ 40 = 17.8 A/μs.
•This results in a characteristic impedance of Rp = du/dt / di/dt = 2000 / 17.8 = 112 ohms
•The capacitance Cp in parallel to the characteristic impedance is rather small: in the nF
range.
•This capacitance Cp causes a delay for the rate of rise of the recovery voltage because
immediately after current interruption this capacitance must be charged.
•The value of this time delay is also specified in the IEC 60056, and for a rate of rise of
2000 V/μs connected with the 100 percent duty the delay time is 2 μs.
•The value of the time delay equals the RC-time of Cp and Rp, and in this way the value
of the capacitance Cp can be calculated.
6. Surge Arresters
7. Transmission Capacitor Bank
Technologies
Series capacitors
Shunt capacitor units are connected from phase to neutral or across
the load. Series capacitors are connected in series in the circuit and
hence carry the full line current.
>> the voltage across the shunt capacitor remains constant, and the
drop across the series bank changes with load.
Shunt compensation.
Series compensation.
SERIES CAPACITORS ON RADIAL FEEDERS
Radial feeder circuit.
Radial feeder circuit with series capacitor.
The corresponding approximate voltage drop (VD’:
If XC = XL, then the voltage drop is IR cos θ. In practical applications, XC is
chosen to be smaller than XL in order to avoid overcompensation.
Using kVA of the sending and receiving ends, the voltage relation can be
calculated as:
Qc is the reactive power supplied
by the series capacitor bank.
The series capacitors are used on long
transmission lines to increase the power
transfer capability and to improve system
stability.
Series capacitor scheme with spark gap and
varistor protection.
for a given phase angle difference between the voltages ,the power transfer is
greater with a series capacitor.
Thus, by making a greater
interchange of power possible, the
normal load transfer and the
synchronizing power flowingduring
transient conditions are increased,
thereby improving stability.
Power transfer of a line without and with series
capacitors.
Fig.02 Single line diagram for MOV protected
Fig.01 Single line diagram of spark gap series capacitor bank.
protected series capacitor bank.
The single gap scheme (Fig. 1) can be called the original
series capacitor scheme. It is simple and is used mainly
where there is only one transmission line. In cases where
there are two or more parallel lines, the MOV scheme (Fig.
2) is normally used.
In case of faults outside the line section where the series
capacitor bank is located, the MOV will protect the
capacitors but the bank will not be bypassed. This will
increase the stability of the transmission system.
Fig. 03 Single line diagram for a
thyristor controlled series capacitor The thyristor controlled scheme may be used to dampen
(TCSC) bank. oscillations in the line, when the weak network does not
dampen the oscillations or these do not dampen sufficiently.
Equipment founded on the series capacitor bank installations in service in
the utility electrical high voltage network are:
• Capacitor units;
• Spark gap;
• By-pass circuit breaker;
• Damping circuit (reactor and resistor);
• By-pass isolator;
• Line isolator;
• Sensing devices (voltage transformers, current transformers, etc.);
• Control system;
• Protection system;
• Platform;
• Insulators; and
• Steelwork.
The capacitor units provide the reactive power component required for achieving
the compensation function. The spark gap and by-pass circuit breaker (connected in
parallel over the capacitors) are used to protect the complete series capacitor
against any over voltage condition that may be experienced as a result of any fault
condition.
The damping circuits provides damping out of the high frequency inrush currents
that will be present during the operation of the spark gap and/or the by-pass circuit
breaker produced by the fault condition and the discharge of the capacitor units into
the protective primary equipment.
The by-pass and line isolators are used for isolating the series capacitor bank,
after it has been de-energised, during outage intervals for the purpose of
maintenance.
The control and protection systems speak for its self as to basically facilitate for
the control and protection functions needed for the proper operation of the series
capacitor bank. The sensing devices provide the necessary input signals for the
control and protection systems.
The platform, support insulators and associated steel structures provide for
the mechanical construction to house the associated equipment and to provide for
the basic insulation level needed in the series capacitor bank.
Brief History
• 1920s; Applying capacitors becomes general practice with externally
fused capacitors
• Until early 1930s, capacitor elements made of tin or lead foil, linen paper
and mineral oil
• Mid 1930s; Wood pulp paper (Kraft paper)
• Mid 1940s; Chlorinated aromatic hydrocarbons (PCB) and internally
fused capacitors
• Late 1960s; Paper-Film dielectric (Polypropylene)
• 1971; All-Film dielectric
• 1975; Non-PCB aromatic hydrocarbon
• 1989; Fuseless capacitor banks
Capacitor Unit Design
Fuseless or
Major Insulation
Externally Fused
Element
Series Section
Capacitor Unit Design
Internally Fused
Capacitor Elements
Internal Connections
Extended Foil Mechanical Crimp
Patented
Mechanical Crimp
Advantages
• The thickness across the pack is smooth, allowing a high
stacking factor and reducing the possibility of film or foil damage.
• Very low resistance foil-to-foil connection on every turn for even
current distribution throughout the element.
• The crimp connection is significantly stronger than other
connection methods resulting in improved performance during
high inrush or discharge transients. Allows for 10 or 15 kA fuse
coordination and a unified and definite tank rupture curve.
• Each individual joint can be tested in the factory.
Design Equations
2
V
O
Q O =Q R
V R
Where:
QO = Operating Reactive Power
QR = Rated Reactive Power
VO = Operating Voltage
VR = Rated Voltage
Design Equations
f
O
Q O =Q R
f R
Where:
QO = Operating Reactive Power
QR = Rated Reactive Power
fO = Operating Frequency
fR = Rated Frequency
Capacitance & Temperature
Capacitance vs Dielectric Temperature
1.04
1.03
1.02
1.01
1
0.99
0.98
Relative Capacitance
0.97
0.96
-60 -50 -40 -30 -20 -10 0 10 20 30 40 50 60
Dielectric Temperature (C)
Tank Rupture
Energy Handling Capability
t
E= Ri 2 dt
0
Where:
E = Energy dissipated in capacitor unit
R = Series Resistance
i = Current
t = time
Tank Rupture
Tank Rupture Curves
• Unified: All capacitor sizes share same curve
• Definite: Not probabilistic
EX-7L
Defined through 10 kA, I2t withstand = 2×106 A2 sec
EX-D
Defined through 15 kA, I2t withstand = 5.6×106 A2 sec
EX-7L Tank Rupture Curve
Current
Time
10 kA, 1.2 Cycle
Capacitor Losses
Sources of Losses
• Discharge resistor
• Internal fuses
• Dielectric
• Other I2R
Capacitor Tank
• 409 stainless steel stabilized with titanium.
• All robotic TIG welding with 308L stainless
steel filler wire.
• Light-gray or brown, wet-process porcelain
bushings soldered to tank.
• Tin-plated brass bushing terminal.
• Brass ground stud brazed to tank.
Robotic Tank Welding
Robotic Tank Welding
Welded Hanger
Leak Testing
Helium Mass Spectrometer
Leak Testing
HMS Leak Detection sensitivity
10-7 cc/sec
Grit Blasting
• Grit blast surface prep before primer coat
• Detergent wash, rinse and forced air dry
• Robotic spray application of:
• Two-part high solids epoxy primer
• Oven cure primer (43°C)
• Two-part high solids urethane
• Oven Cure (43°C)
Grit Blasting
Grit Blasted Unit
Grit Blasting
Before and After
Capacitor Coating System
• Exceeds ANSI C57.12.31 Polemount Standard
• Meets or exceeds ANSI C57.12.29 Coastal
Coatings Standard (1500 Hour Salt Fog)
• Robot spray process provides consistent
application and coverage
• Superior adhesion, thickness, and coverage
versus hand applied coatings
• Reduces HAP emissions 50%
Robotic Tank Painting
Capacitor Fusing
Types of Capacitor Fusing
• External (Expulsion or Current Limiting)
• Internal
• Fuseless
External Fusing
Eight, 50 Mvar,
154 kV Banks
in parallel
External Fusing
Capacitor Fusing
Why do we fuse
capacitors?
Capacitor Unit Design
Fuseless or
Major Insulation
Externally Fused
Element
Series Section
Capacitor Unit Design
Internally Fused
Dielectric Failure
The Safe Failure Mode of the All-Film Capacitor
• Breakdown of the polypropylene dielectric
• Arc from electrode to electrode
• Stored energy discharges into the fault
• Arc punctures several layers of film and foil
• Film melts and recedes from the puncture point
• Several layers of the aluminum foil touch
• The aluminum foil electrodes weld together
• A stable electrical joint is formed
All-Film Field Experience
• Safe failure mode allows use of higher voltage units
• Utility measurements indicate that partially failed capacitor units can
operate indefinitely without case swelling or fuse operation
Fusing Issues
• Type of Failure
• Parallel Energy
• Voltage
• Unbalance Detection
• Harmonic Filter Tuning
• Maintenance
• Losses
Type of Failure
• Dielectric Failure
• Insulation Failure
Dielectric Failure
Externally Fused
• As elements in an externally fused capacitor unit
fail, the series section is shorted.
• As series sections are shorted, the impedance of
the unit goes down and thus the current in the
capacitor unit goes up.
• After enough series section failures, the capacitor
current causes the external fuse to operate.
• If the capacitor unit fails to a short circuit, the
discharge of the parallel connected capacitors help
the fuse operate quickly.
Dielectric Failure
Externally Fused
I
Dielectric Failure
Internally Fused
• Each element is individually fused.
• When an element fails, it becomes a short circuit
and the parallel connected elements discharge
into the failed element.
• This discharge through the fuse causes a current
limiting action and the failed element is isolated.
• This discharge is required for proper fuse
operation.
Insulation Failure
Externally Fused
• The fault current resulting from an insulation
failure will operate the external fuse.
• After the operation of the fuse, the bank
remains in service.
Insulation Failure
Internally Fused
• Internal fuses provide no protection for insulation
failures and the bank must be removed from
service rapidly to minimize damage.
• Parallel connected energy is not a concern for a
typical dielectric failure. However, it is of great
concern for insulation failures due to the
probability of tank rupture.
• Insulation failures in banks with capacitor unit
cases grounded may result in fault to ground.
Insulation Failure
Fuseless
• As there are no external fuses, the bank must be
removed from service rapidly to minimize damage.
• Capacitor units are not connected in parallel so the
energy discharged into the fault will be very low
thus minimizing the probability of tank rupture.
Parallel Energy
• Must be within the capability of external
expulsion fuses.
• Not an issue with external current limiting fuses.
• Typically not an issue with internal fusing except
for insulation failures.
• Not an issue with fuseless banks because
capacitor units are not connected in parallel.
Voltage
• For both external and internal fusing, the voltage across
the fuse must be within the rating of the fuse.
• After a fuse has operated, the open gap must be able to
withstand the continuous voltage and any transients.
• For an externally fused bank, the open gap is very large
and easily capable of withstanding the largest transients.
• For an internally fused bank, the open gap is very small
and contaminated with products of the fuse operation. The
withstand of the open gap is of great concern.
Unbalance Detection
Purpose
1. To increase bank availability by warning
personnel of problems in the bank.
2. Remove the bank from service before
severe damage occurs.
Unbalance Protection
Externally Fused
Primary
Safe failure mode of all-film dielectric
Secondary
External Fuse Operation
Final
Protective Relaying
Unbalance Protection
Internally Fused
Primary
Internal Fuse Operation
Final
Protective Relaying
Unbalance Protection
Fuseless
Primary
Safe failure mode of all-film dielectric
Secondary
Remaining series sections limit voltage and current
Final
Protective Relaying
Unbalance Detection
Sensitivity
• Externally Fused: External fuse operations (108 fuses)
• Fuseless: Series section short (240 series sections)
• Internally Fused: Element fuse operation (2,880 fuses)
The above figures show that the sensitivity of the
unbalance detection scheme needs to be greatest for
the internally fused bank.
Ambiguous Indications
Occurs when canceling failures occur in
the bank which result in an indication that
the bank is balanced.
Ambiguous Indication
C C
IU=0
C C
Ambiguous Indication
C C
IU>
0
C C+C
Ambiguous Indication
C C+C
IU=
0
C C+C
Unbalance Detection
X & Y Banks
Fuseless è The unbalance detection scheme will
detect the first failure of a series section to
a short circuit.
è The unbalance detection scheme will not
Internally Fused detect the first internal fuse operation.
Due to the danger of ambiguous indications, periodic
capacitance measurements of each unit is required for the
internally fused banks.
Harmonic Filter Tuning
Externally Fused
• Dielectric failures cause the capacitance of the
bank to increase. (Decreases tuning point)
• Fuse operations cause the capacitance of the
bank to decrease. (Increases tuning point)
• Typically large steps of capacitance change
necessitating an evaluation of the effects.
• Typically alarm on 1st fuse operation and trip on
the 2nd.
Harmonic Filter Tuning
Internally Fused
• Fuse operations cause the capacitance of the
bank to decrease. (Increases tuning point)
• Smaller change in capacitance than for an
externally fused bank.
• Detection of the capacitance change is very
problematic.
• Documented problems with undetected
capacitance changes resulting in parallel
resonance.
Harmonic Filter Tuning
Fuseless
• Dielectric failures cause the capacitance of the bank
to increase. (Decreases tuning point)
• Smaller change in capacitance than for an externally
fused bank.
• Only the fuseless capacitor bank results in only a
decrease in the tuning point of the filter with
dielectric failures typically resulting in a shift away
from a parallel resonance with the system
Maintenance
Annual maintenance to check for:
• Bulged / leaking capacitor units
• Contaminated / damaged porcelain
• Foreign matter in the bank
Maintenance
Externally Fused
• Only the maintenance mentioned in the previous
slide is recommended.
• Location of failed capacitor units is accomplished
very quickly with a visual inspection.
Maintenance
Internally Fused
• Annual maintenance to locate partially failed
capacitor units is required due to the issue of
ambiguous indications.
• Locating failed capacitor units requires the
measurement of every capacitor unit and is
very time consuming and problematic.
Capacitance & Temperature
Capacitance vs Dielectric Temperature
1.04
1.03
1.02
1.01
1
0.99
0.98
Relative Capacitance
0.97
0.96
-60 -50 -40 -30 -20 -10 0 10 20 30 40 50 60
Dielectric Temperature (C)
Maintenance
Fuseless
• Ambiguous indications, may result in annual visual
inspection.
• Location failed capacitor units requires only
measurements to locate the string containing the
faulty unit followed by measurements of the units
within the string.
Fuseless Capacitor Banks
145 kV, 100 Mvar
• 4 + 4 Strings
• 8 Units / String
• Unit Rating:
521 kvar
10,464 V
158 kV, 90.7 Mvar
158 kV, 90.7 Mvar
• 3 + 3 Strings
• 12 Units / String
• Unit Rating:
420 kvar
7.6 kV
Not a New Technology
• Fuseless capacitor banks are an application
of the all-film technology introduced by
McGraw-Edison in 1971.
• Cooper Power Systems first fuseless bank
was delivered in 1989.
• Fuseless capacitor banks are the ―Standard‖
in the United States, Canada and South
Africa.
Capacitor Unit Design
Fuseless or
Major Insulation
Externally Fused
Element
Series Section
Fuseless Capacitors
How can we apply the
all-film capacitor
without fuses?
Fuseless String
String of 4 Series Connected Capacitor Units
Capacitor
Unit
32 Series Sections from phase-to-ground
Fuseless String
One Shorted Series Section
Capacitor
Unit
32 Series Sections from phase-to-ground
SS 32
OV = OV = = 1.03 PU
SS - F 32 - 1
Design Considerations
• Rated voltage 24 kV for best economics
• Maximum current per string of 75 A
• Capacitor units connected in series
Applications
• Shunt Capacitor Banks
• Series Capacitor Banks
• Harmonic Filters
Shunt Capacitor Banks
• Typically applied at 24 kV
• Have been applied as low as 12 kV by de-rating
capacitor units
Series Capacitor Banks
• Saves platform space
• Reduces weight on platform
• Parallel energy not a concern
• Typically applied at Vc 50 kV
Harmonic Filters
Harmonic Filter Tuning Point
1
f =
2 LC
• Small change in tuning point
• Shifts tuning away from parallel resonance
• Low losses = sharper tuning
Protective Relaying
• Overcurrent
• Overvoltage
• Unbalance
Protective Relaying
Overcurrent and overvoltage protection
of fuseless capacitor banks is identical
to that of externally and internally fused
banks.
Maintenance
• Inspection
• Locating defective capacitor units
• Cleaning of bushings / insulators
Disadvantages
• No external fuses to protect for insulation failures
• Locating defective capacitor units
• Sensitive unbalance relaying required
• Knowledge of capacitor unit internal construction necessary
Advantages
Advantages of Fuseless over Externally Fused Capacitor Banks
• Cost from 10 to 30% less
• Approximately 50% less substation space required
• No spurious fuse operations
• No coordination of fuse TCC with relaying
• Parallel energy not a concern
• Low resulting over-voltage with element failure
• D C for harmonic filters
• Animal proofing / Less bus bars
• Simplicity
Advantages
Advantages of Fuseless over Internally Fused Capacitor Banks
• Cost from 10 to 30% less
• 40% less losses
• Easier more reliable unbalance relaying
• D C for harmonic filters
• Low resulting over-voltage with element failure
• Longer life
• Easier to locate partially failed units
• Simplicity
Unbalance Protection
Cooper Power Systems
McGraw Edison Power Capacitors
Greenwood, SC USA
Purpose
To increase bank availability by warning
personnel of problems (Failures) in the bank
and removing the bank from service before
severe damage occurs.
Failure Events
• Dielectric Failures
• Bushing / Insulator Flashover
• Major Insulation Failure
Fuseless Bank
Capacitor
Unit
32 Series Sections from phase-to-ground
One Shorted Series Section
Capacitor
Unit
32 Series Sections from phase-to-ground
110kV Configuration
110kV Configuration
66kV Configuration
66kV Configuration
Types of Unbalance
• System
• Inherent
• Internal Failures
Unbalance Relaying
Criteria
Fuseless Banks
• Notify personnel (Alarm) in the event of the first series
section short (if possible).
• Remove the bank from service (Trip) when enough series
sections have shorted in a string to result in greater than a
110% overvoltage on the remaining series sections.
• Remove the bank from service (Trip) when the number of
shorted series sections in a string equal that contained in
one capacitor unit.
8. Intro to High Voltage
Direct Current
(HVDC) Technologies
HVDC advantages over
AC transmission
High Voltage Direct Current HVDC
• High voltage DC connection
– No reactive losses
• No stability distance limitation
• No limit to underground cable length
• Lower electrical losses
P=U I
– 2 cables instead of 3 DC DC
– Synchronism is not needed
• Connecting different frequencies
• Asynchronous grids (UCTE – UK)
• Black start capability? (New types, HVDC light)
– Power flow (injection) can be fully controlled
• Renewed attention of the power industry
History of HVDC
HVDC Configurations:
Transmission modes (I)
• Back to back • Monopolar
(Sea)
• Bipolar • Multiterminal
+
-
HVDC Configurations:
Transmission modes (II)
LCC HVDC
• Thyristor or mercury-arc
valves
• Reactive power source
needed
• Large harmonic filters needed
VSC HVDC
• IGBT valves
• P and Q (or U) control
• Can feed in passive networks
• Smaller footprint
• Less filters needed
HVDC Example- Norned cable
HVDC Example- Norned cable: schematic
HVDC Example- Norned cable: sea cable
HVDC Example- Garabi back to back
HVDC Example- Garabi back to back (4x)
VSC HVDC Example- Murray link
• Commissioning
year:2002
• Power rating: 220 MW
AC
• Voltage:132/220 kV
• DC Voltage:+/- 150 kV
• DC Current: 739 A
• Length of DC cable:2 x
180 km
VSC HVDC Example- Troll
• Commissioning year:
2005
• Power rating: 2 x 42
MW AC Voltage:132 kV
at Kollsnes, 56 kV at
Troll
• DC Voltage: +/- 60 kV
• DC Current: 350 A
• Length of DC cable:4 x
70 km
HVDC- Current sizes
Các file đính kèm theo tài liệu này:
- bai_giang_trang_thiet_bi_dien_tren_he_thong_truyen_tai_dien.pdf